Following the successful ROV inspection and survey completed last year, we are proud to share that the next phase of the dam project in Asia has now been successfully completed.

At a depth of 42 metres, our team successfully removed sediment that was blocking the dam’s intake structures. Using a dredge pump, we carried out this technical operation, clearing the way for the next phase of the project.

With the intakes now fully accessible, we are moving ahead at full pace with equipment preparation and the fabrication of 150 tonnes of bulkhead and steel stabilisation structures.

We’re excited to continue sharing progress as the project advances. Stay tuned for more updates!